Balcony renovation on our North York condo unit — waterproofing failure discovered, full rebuild cost

Our North York condo unit had a 120 sq ft balcony that was visibly failing — tiles lifting, grout cracking, and a persistent water stain on the unit below us (our responsibility under the condo declaration). Sharing the full experience.

Assessment:
Retained a balcony waterproofing specialist. He removed two tiles and confirmed the waterproofing membrane underneath had failed — completely debonded from the concrete in multiple areas. Original installation was from 2001 — the membrane had served its life.

What the condo required:

  • Formal notice to condo board before starting (7 days notice + description of work)
  • Contractor had to provide proof of insurance naming the condo corporation
  • Work had to occur weekdays only, 8 AM to 5 PM (no weekend noise)
  • All debris bagged before transport through common areas

Scope:

  • Full tile removal
  • Membrane removal and substrate inspection (found minor concrete spalling — repaired with polymer-modified mortar)
  • New traffic-rated membrane (SOPREMA Sopralene Stick, 60-mil)
  • 20x20 porcelain tile with frost-rated rating (absorption under 0.5%)
  • New Schluter BARA edge profile at balcony edge
  • Reinstall railing (original aluminum, in good condition)

Cost:

  • Contractor labour and membrane supply: $8,400
  • Tile supply (36 sq ft coverage including cuts): $780
  • Tile installation: $1,200
  • Total: $10,380

Post-work:
Zero water intrusion after our first full winter including an ice storm event. The unit below confirmed no further staining.

The lesson: the tile is cosmetic. The membrane is the building envelope. Get the membrane right.