# Sharing My Contractor Vetting Process — How I Found Our GC After 3 Bad Experiences

**URL:** <https://home.renovation.reviews/t/sharing-my-contractor-vetting-process-how-i-found-our-gc-after-3-bad-experiences/46341>\
**Category:** Ontario\
**Created:** [April 25, 2026, 7:23pm UTC](https://home.renovation.reviews/t/sharing-my-contractor-vetting-process-how-i-found-our-gc-after-3-bad-experiences/46341 "2026-04-25T19:23:58Z")\
**Posts on this page:** 1\
**Page:** 1

<div class="post-metadata">

**Author:** ![system](https://home.renovation.reviews/user_avatar/home.renovation.reviews/system/32/77_2.png) [@system](https://home.renovation.reviews/u/system)\
**Post date:** [April 25, 2026, 7:23pm UTC](https://home.renovation.reviews/t/sharing-my-contractor-vetting-process-how-i-found-our-gc-after-3-bad-experiences/46341/1 "2026-04-25T19:23:58Z")

</div>

After three frustrating contractor experiences in previous renovations, I spent considerable time developing a proper vetting process before our current project (full main floor renovation + basement suite). Sharing in case it helps others avoid the same mistakes.

**What went wrong before:**

1. Contractor abandoned project when 60% complete (cash flow problems on his end, no communication)
2. Contractor who didn’t pull permits — we discovered 18 months later during refinancing
3. Contractor who substantially under-quoted then added change orders to make up the difference

**My current process (which I now follow rigorously):**

_Step 1:_ Only consider contractors with verifiable recent references from projects in the past 2 years. This forum and neighbour recommendations are my only sources now. No Kijiji, no Facebook Marketplace, no door-knockers.

_Step 2:_ I call all three references and ask specific questions: final cost vs. original quote, timeline performance, how they handled problems, would they use again.

_Step 3:_ I verify WSIB (check online, not just take their word), get the actual insurance certificate (not just “I have insurance”), verify their HST number.

_Step 4:_ I require a detailed written contract with specific materials and payment tied to completion milestones. If they resist this, they’re off the list.

_Step 5:_ I hold 10% until punch list is complete and all inspections are passed. This is in the contract.

Our current contractor has been excellent — 4 weeks in, no surprises, permits in place, proactive communication. Worth the extra vetting time.