# Pulled permits for our deck in Mississauga — here is the actual process and timeline

**URL:** <https://home.renovation.reviews/t/pulled-permits-for-our-deck-in-mississauga-here-is-the-actual-process-and-timeline/46745>\
**Category:** Ontario\
**Created:** [April 26, 2026, 4:28pm UTC](https://home.renovation.reviews/t/pulled-permits-for-our-deck-in-mississauga-here-is-the-actual-process-and-timeline/46745 "2026-04-26T16:28:03Z")\
**Posts on this page:** 1\
**Page:** 1

<div class="post-metadata">

**Author:** ![system](https://home.renovation.reviews/user_avatar/home.renovation.reviews/system/32/77_2.png) [@system](https://home.renovation.reviews/u/system)\
**Post date:** [April 26, 2026, 4:28pm UTC](https://home.renovation.reviews/t/pulled-permits-for-our-deck-in-mississauga-here-is-the-actual-process-and-timeline/46745/1 "2026-04-26T16:28:03Z")

</div>

We just went through the deck permit process in Mississauga for a 400 sq ft composite deck with aluminum glass railing. Sharing the process because I couldn’t find a clear breakdown anywhere.

**Application:**

- Submitted online through Mississauga’s ePlans portal
- Required: site plan (I drew it in Google Drawings, it was accepted), deck framing plan showing joist/beam sizes, footing locations
- Engineer’s stamp: NOT required for standard residential decks — only if over a certain size or unusual configuration

**Timeline:**

- Submitted: March 11
- Permit issued: March 28
- 12 business days — much faster than I expected

**Inspections required:**

1. Footing inspection before pouring concrete (or setting helical piers)
2. Framing inspection before decking goes on
3. Final inspection when complete

**Cost:**

- Permit fee: $175 flat (under 50 sq m)
- Inspector was thorough on the footing inspection — ours were 1.4m deep (we oversized slightly for peace of mind)

**Contractor vs DIY:**

- We used a contractor for everything except the permit application, which I did myself
- Total deck cost: $27,400 (Trex Transcend decking, aluminum/glass railing, aluminum posts)

Anyone else done permits through Mississauga’s ePlans? Curious if others found the portal easy to use.