# Home Insulation Upgrades Ontario - Attic, Walls, Basement and ROI

**URL:** <https://home.renovation.reviews/t/home-insulation-upgrades-ontario-attic-walls-basement-and-roi/46697>\
**Category:** DIY & Tutorials\
**Created:** [April 26, 2026, 3:36pm UTC](https://home.renovation.reviews/t/home-insulation-upgrades-ontario-attic-walls-basement-and-roi/46697 "2026-04-26T15:36:14Z")\
**Posts on this page:** 1\
**Page:** 1

<div class="post-metadata">

**Author:** ![system](https://home.renovation.reviews/user_avatar/home.renovation.reviews/system/32/77_2.png) [@system](https://home.renovation.reviews/u/system)\
**Post date:** [April 26, 2026, 3:36pm UTC](https://home.renovation.reviews/t/home-insulation-upgrades-ontario-attic-walls-basement-and-roi/46697/1 "2026-04-26T15:36:14Z")

</div>

Did a full energy audit on our 1978 Mississauga home and ended up doing staged insulation upgrades over 18 months. Posting the full results.

**The Audit (EnerGuide)**

Our pre-retrofit EnerGuide score was 56. The auditor ranked our upgrades by ROI:

1. Attic air sealing + insulation upgrade (highest ROI)
2. Basement rim joist spray foam
3. Main floor air sealing
4. Main wall upgrade (lowest immediate ROI, most disruptive)

**What We Did and What It Cost**

**Attic - $3,800**  
Existing blown fibreglass was R-22. Air sealed all penetrations (pot lights, plumbing stacks, top plates) then added blown cellulose to R-60. This was the best money we spent.

**Basement rim joists - $1,100**  
2-inch closed-cell spray foam applied to all rim joist bays. Major reduction in cold floors and drafts.

**Main floor air sealing - $650**  
Contractor sealed around all electrical outlets, switches, and penetrations with foam and acoustic sealant.

**Total: $5,550**

**Results**

Post-retrofit EnerGuide score: 71 (up from 56). Natural gas bills down approximately $780/year. Payback period roughly 7 years.

**Greener Homes Grant**

We received $2,600 back through the Canada Greener Homes Grant. Program availability changes so check nrcan.gc.ca. You MUST do the EnerGuide pre-assessment before work begins to qualify.

**Key Takeaway**

Do the attic first. The ROI is highest and the disruption is minimal compared to wall insulation.