# Home Addition Project in Mississauga - Rear Bump-Out Timeline and Real Cost

**URL:** <https://home.renovation.reviews/t/home-addition-project-in-mississauga-rear-bump-out-timeline-and-real-cost/46710>\
**Category:** Ontario\
**Created:** [April 26, 2026, 3:51pm UTC](https://home.renovation.reviews/t/home-addition-project-in-mississauga-rear-bump-out-timeline-and-real-cost/46710 "2026-04-26T15:51:14Z")\
**Posts on this page:** 1\
**Page:** 1

<div class="post-metadata">

**Author:** ![system](https://home.renovation.reviews/user_avatar/home.renovation.reviews/system/32/77_2.png) [@system](https://home.renovation.reviews/u/system)\
**Post date:** [April 26, 2026, 3:51pm UTC](https://home.renovation.reviews/t/home-addition-project-in-mississauga-rear-bump-out-timeline-and-real-cost/46710/1 "2026-04-26T15:51:14Z")

</div>

Completed a 280 sq ft single-storey rear addition on our 1978 Mississauga home. Kitchen expanded significantly and we added a proper mudroom. Documenting the process for others researching additions.

**Project Scope**

Extending the rear of the house 14 feet by 20 feet (280 sq ft). Scope included:

- New foundation (frost-protected shallow foundation)
- Framing, insulation (OBC-compliant: walls R-24, ceiling R-60)
- Windows (3 new)
- Roof tie-in to existing
- Kitchen expansion into new space (new island, extended cabinets)
- Mudroom with bench, cubbies, floor tile

**Timeline**

Application submitted: August 2025  
Permit issued: October 2025 (9 weeks - longer than expected, Mississauga was backlogged)  
Construction start: October 28, 2025  
Substantial completion: February 14, 2026  
Final inspection: March 5, 2026

Total from application to final: 7 months (5 months construction, 2 months permits)

**Cost Breakdown**

Architecture drawings: $4,800  
Structural engineer: $2,200  
Permit fees: $3,100  
Foundation and framing: $38,000  
Windows: $5,400  
Roofing (new section + tie-in): $7,200  
Insulation + drywall + tape: $8,600  
Flooring (tile in mudroom, LVP in kitchen extension): $4,200  
Kitchen modifications (cabinets, island, countertop additions): $12,800  
Mudroom millwork: $6,400  
Mechanical/electrical changes: $5,100  
Painting: $2,400  
Total: $100,200

Per sq ft: $358/sq ft - within the $300-$500 range I had budgeted for.

**The Contingency Was Used**

Budgeted $8,000 contingency. Used $5,200 of it on an unexpected sewer cleanout relocation that the site exposed.

Would do it again - the addition transformed how the house functions.