# Concrete Contractor is asking for a draw of 66% AFTER first day of work saying he will be getting the concrete and then full balance due after he pulls the forms off, is this standard?

**URL:** <https://home.renovation.reviews/t/concrete-contractor-is-asking-for-a-draw-of-66-after-first-day-of-work-saying-he-will-be-getting-the-concrete-and-then-full-balance-due-after-he-pulls-the-forms-off-is-this-standard/30547>\
**Category:** Contractors\
**Created:** [September 2, 2025, 2:26am UTC](https://home.renovation.reviews/t/concrete-contractor-is-asking-for-a-draw-of-66-after-first-day-of-work-saying-he-will-be-getting-the-concrete-and-then-full-balance-due-after-he-pulls-the-forms-off-is-this-standard/30547 "2025-09-02T02:26:09Z")\
**Posts on this page:** 9\
**Page:** 1

<div class="post-metadata">

**Author:** ![Onyxx](https://home.renovation.reviews/letter_avatar_proxy/v4/letter/o/da6949/32.png) [@Onyxx](https://home.renovation.reviews/u/Onyxx)\
**Post date:** [September 2, 2025, 2:26am UTC](https://home.renovation.reviews/t/concrete-contractor-is-asking-for-a-draw-of-66-after-first-day-of-work-saying-he-will-be-getting-the-concrete-and-then-full-balance-due-after-he-pulls-the-forms-off-is-this-standard/30547/1 "2025-09-02T02:26:09Z")

</div>

I’m in Southern California, and accustomed to the CSLB rules of no more than 10% or $1,000. He has not done 66% of the work. These seems a bit high to me and I’m not comfortable with this route, was not outlined in his quote either.

---

<div class="post-metadata">

**Author:** ![Jakurasmith](https://home.renovation.reviews/user_avatar/home.renovation.reviews/jakurasmith/32/585_2.png) [@Jakurasmith](https://home.renovation.reviews/u/Jakurasmith)\
**Post date:** [September 2, 2025, 2:40am UTC](https://home.renovation.reviews/t/concrete-contractor-is-asking-for-a-draw-of-66-after-first-day-of-work-saying-he-will-be-getting-the-concrete-and-then-full-balance-due-after-he-pulls-the-forms-off-is-this-standard/30547/2 "2025-09-02T02:40:27Z")

</div>

Thanks for sharing this with us

---

<div class="post-metadata">

**Author:** ![ThomasWood](https://home.renovation.reviews/user_avatar/home.renovation.reviews/thomaswood/32/12461_2.png) [@ThomasWood](https://home.renovation.reviews/u/ThomasWood)\
**Post date:** [September 2, 2025, 1:52pm UTC](https://home.renovation.reviews/t/concrete-contractor-is-asking-for-a-draw-of-66-after-first-day-of-work-saying-he-will-be-getting-the-concrete-and-then-full-balance-due-after-he-pulls-the-forms-off-is-this-standard/30547/3 "2025-09-02T13:52:53Z")

</div>

Wow this is very useful thank you

---

<div class="post-metadata">

**Author:** ![Succy](https://home.renovation.reviews/letter_avatar_proxy/v4/letter/s/ccd318/32.png) [@Succy](https://home.renovation.reviews/u/Succy)\
**Post date:** [September 2, 2025, 5:54pm UTC](https://home.renovation.reviews/t/concrete-contractor-is-asking-for-a-draw-of-66-after-first-day-of-work-saying-he-will-be-getting-the-concrete-and-then-full-balance-due-after-he-pulls-the-forms-off-is-this-standard/30547/4 "2025-09-02T17:54:41Z")

</div>

Thanks for the information

---

<div class="post-metadata">

**Author:** ![Theodore\_3456](https://home.renovation.reviews/user_avatar/home.renovation.reviews/theodore_3456/32/2821_2.png) [@Theodore\_3456](https://home.renovation.reviews/u/Theodore_3456)\
**Post date:** [September 3, 2025, 5:59am UTC](https://home.renovation.reviews/t/concrete-contractor-is-asking-for-a-draw-of-66-after-first-day-of-work-saying-he-will-be-getting-the-concrete-and-then-full-balance-due-after-he-pulls-the-forms-off-is-this-standard/30547/5 "2025-09-03T05:59:59Z")

</div>

You just be careful with your dealings

---

<div class="post-metadata">

**Author:** ![Succy](https://home.renovation.reviews/letter_avatar_proxy/v4/letter/s/ccd318/32.png) [@Succy](https://home.renovation.reviews/u/Succy)\
**Post date:** [September 3, 2025, 2:57pm UTC](https://home.renovation.reviews/t/concrete-contractor-is-asking-for-a-draw-of-66-after-first-day-of-work-saying-he-will-be-getting-the-concrete-and-then-full-balance-due-after-he-pulls-the-forms-off-is-this-standard/30547/6 "2025-09-03T14:57:18Z")

</div>

Thanks for this buddy

---

<div class="post-metadata">

**Author:** ![Tim\_Michael1](https://home.renovation.reviews/user_avatar/home.renovation.reviews/tim_michael1/32/6294_2.png) [@Tim\_Michael1](https://home.renovation.reviews/u/Tim_Michael1)\
**Post date:** [September 6, 2025, 9:13am UTC](https://home.renovation.reviews/t/concrete-contractor-is-asking-for-a-draw-of-66-after-first-day-of-work-saying-he-will-be-getting-the-concrete-and-then-full-balance-due-after-he-pulls-the-forms-off-is-this-standard/30547/7 "2025-09-06T09:13:59Z")

</div>

Okay Thank you for this bro

---

<div class="post-metadata">

**Author:** ![MichaelRobert](https://home.renovation.reviews/letter_avatar_proxy/v4/letter/m/da6949/32.png) [@MichaelRobert](https://home.renovation.reviews/u/MichaelRobert)\
**Post date:** [September 7, 2025, 2:12am UTC](https://home.renovation.reviews/t/concrete-contractor-is-asking-for-a-draw-of-66-after-first-day-of-work-saying-he-will-be-getting-the-concrete-and-then-full-balance-due-after-he-pulls-the-forms-off-is-this-standard/30547/8 "2025-09-07T02:12:04Z")

</div>

Glad to come across this

---

<div class="post-metadata">

**Author:** ![Bobby\_Michael](https://home.renovation.reviews/user_avatar/home.renovation.reviews/bobby_michael/32/2057_2.png) [@Bobby\_Michael](https://home.renovation.reviews/u/Bobby_Michael)\
**Post date:** [September 7, 2025, 2:38am UTC](https://home.renovation.reviews/t/concrete-contractor-is-asking-for-a-draw-of-66-after-first-day-of-work-saying-he-will-be-getting-the-concrete-and-then-full-balance-due-after-he-pulls-the-forms-off-is-this-standard/30547/9 "2025-09-07T02:38:18Z")

</div>

Thanks for coming up with this