# Asbestos Discovery During Our Toronto Bathroom Renovation - What Happened

**URL:** <https://home.renovation.reviews/t/asbestos-discovery-during-our-toronto-bathroom-renovation-what-happened/46728>\
**Category:** Ontario\
**Created:** [April 26, 2026, 4:07pm UTC](https://home.renovation.reviews/t/asbestos-discovery-during-our-toronto-bathroom-renovation-what-happened/46728 "2026-04-26T16:07:42Z")\
**Posts on this page:** 1\
**Page:** 1

<div class="post-metadata">

**Author:** ![system](https://home.renovation.reviews/user_avatar/home.renovation.reviews/system/32/77_2.png) [@system](https://home.renovation.reviews/u/system)\
**Post date:** [April 26, 2026, 4:07pm UTC](https://home.renovation.reviews/t/asbestos-discovery-during-our-toronto-bathroom-renovation-what-happened/46728/1 "2026-04-26T16:07:42Z")

</div>

Our bathroom renovation in our 1968 Toronto home took an unexpected turn when we found asbestos. Sharing the experience so others know what to expect if it happens to them.

**The Discovery**

Contractor removed the floor tiles in the bathroom - 9x9 inch white vinyl tiles with black adhesive (classic pattern from the era). He immediately recognized it as a potential asbestos tile situation. Stopped work, did not disturb further.

**Sampling and Testing**

Hired an environmental consultant ($220) who collected samples from 3 locations: the tile material itself, the black mastic adhesive, and a small section of drywall joint compound that was also present in the wall.

Results (5 business days):

- Floor tile: 2.1% chrysotile asbestos (confirmed positive)
- Black mastic: 3.4% chrysotile (confirmed positive)
- Drywall compound: non-detect

**The Abatement**

Type 2 abatement required (friability depends on condition - the mastic was somewhat soft). A Ministry of Labour registered abatement contractor performed the removal:

- Set up poly containment around work area
- Wet methods to suppress fibres during tile removal
- HEPA vacuum and decontamination
- Disposal at approved waste facility

Cost: $2,800 for 65 sq ft of tile removal.

**Timeline Impact**

Added 2 weeks to the project (notification requirements under Ontario Regulation 278/05 have a 1-week advance notice requirement for Type 2 work). Our renovation contractor was able to do other prep work during this period.

**Total Project Impact**

$2,800 abatement + 2 week delay. Not catastrophic but a clear reminder to test before demo in any pre-1980 Ontario home. The testing cost ($220) was the smartest money spent on the project.